Scoresby Co. uses 3 machine hours and 1 direct labor hour to produce Product X. It uses 4 machine hours and 8 direct labor hours to produce Product Y. Scoresby's Assembly and Finishing Departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. How much overhead cost will be charged to the two products? (A) Product X = $720; Product Y = $1,280 (B) Product X = $1,600; Product Y = $4,800 (C) Product X = $880; Product Y = $2,240 (D) Product X = $400; Product Y = $400

+4
Answers (1)
  1. 28 June, 19:59
    0
    (C) Product X = $880; Product Y = $2,240

    Explanation:

    The applied overhead will be calculate by the product of the cost diver and the overhead rate:

    Cost driver for each product:

    Product X 3MH and 1LH

    Product Y 4MH and 8LH

    Overhead rate:

    240 per machine hour

    and 160 per labor hour

    Product X 3MH x $240 + 1LH x $160 = 880

    Product Y 4MH x $240 + 8LH x $160 = 2,240
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Scoresby Co. uses 3 machine hours and 1 direct labor hour to produce Product X. It uses 4 machine hours and 8 direct labor hours to produce ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.