Assume that the Assembly Department allocates overhead using a plantwide overhead rate based on machine hours. How much total overhead will be assigned to a product that requires 1 direct labor hour and 2.5 machine hours in the Assembly Department, and 3.5 direct labor hours and 0.5 machine hours in the Finishing Department?

+5
Answers (1)
  1. 11 June, 01:33
    0
    Instructions are listed below.

    Explanation:

    Giving the following information:

    Assume that the Assembly Department allocates overhead using a plantwide overhead rate based on machine hours.

    The first thing that we need is the predetermined overhead rate. We weren't provided with this information, but I will give the formula and a small example to guide an answer:

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    For example:

    Estimated overhead = $200,000

    Estimated machine hours = 35,000

    Estimated manufacturing overhead rate = 200,000/35,000 = $5.71 per machine hour

    Now, we can allocate overhead:

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Because it is a plantwide overhead rate, we need to sum the total machine hours required:

    Machine hours = 2.5 + 0.5 = 3 machine hours

    Allocated MOH = 5.71*3 = $17.13 per unit
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Assume that the Assembly Department allocates overhead using a plantwide overhead rate based on machine hours. How much total overhead will ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.