Ask Question
6 December, 14:27

In the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task. true or false?

+5
Answers (1)
  1. 6 December, 18:14
    0
    False

    Explanation:

    The statement that says that in the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task is false because the effort is the time a person needs to finish a task while the duration is the period of time that a person has to finish it. For example, an employee has a task that takes forty hours of work to finish it but he has a month to do it. In this case, the effort is forty hours but the task duration is one month.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task. true ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers