Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,400 of direct materials and used $3,900 of direct labor. The job was not finished by the end of September, but needed an additional $2,900 of direct materials in October and additional direct labor of $6,400 to finish the job. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?

+5
Answers (1)
  1. 1 June, 22:15
    0
    Work in process October = $15,700

    Explanation:

    Giving the following information:

    During September, Jaycee Corporation requisitioned $2,400 of direct materials and used $3,900 of direct labor. The job was not finished by the end of September, but needed an additional $2,900 of direct materials in October and additional direct labor of $6,400 to finish the job. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost.

    Work in process = direct material + direct labor + manufacturing overhead

    Work in process = 2,900 + 6,400 + 6,400 = $15,700
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,400 of direct ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers