Madison Inc. uses job order costing for its brand new line of sewing machines. The cost incurred for production during 2017 totaled $18,000 of materials, $9,000 of direct labor costs, and $6,000 of manufacturing overhead applied. The company ships all goods as soon as they are completed which results in no finished goods inventory on hand at the end of any year. Beginning work in process totaled $15,000, and the ending balance is $9,000. During the year, the company completed 25 machines. How much is the cost per machine?

+4
Answers (1)
  1. 16 February, 01:25
    0
    The cost per machine will be $1,560.

    Explanation:

    Cost of materials is given at $18,000.

    The cost of direct labor is $9000.

    The manufacturing overhead cost is $6000.

    Beginning work in process is $15,000.

    The ending balance is $9000.

    The number of machines completed is 25.

    The total cost of making machines will be

    =Cost of materials + cost of direct labor + manufacturing overhead cost+Beginning work in process-ending work in process

    =$ (18000+9000+6000+15000-9000)

    =$39,000

    The cost per machine will be

    =Total cost of making machines / number of machines

    =$39,000/25

    =$1,560
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Madison Inc. uses job order costing for its brand new line of sewing machines. The cost incurred for production during 2017 totaled $18,000 ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.