Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.5 day, and its average queue time is 3.0 days.
Required:
a) What is the Wait Time?
b) What is the Process Time?
c) What is the Inspection Time?
Round your answer to 1 decimal place.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput time is 14.0 days, its ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.