If the labor efficiency variance is unfavorable, then

a. standard hours allowed for the actual output exceeded actual hours.

b. the standard rate exceeded the actual rate.

c. the actual rate exceeded the standard rate.

d. actual hours exceeded standard hours allowed for the actual output.

+1
Answers (1)
  1. 7 March, 12:06
    0
    Answer: The correct answer is "d. actual hours exceeded standard hours allowed for the actual output.".

    Explanation: The variation in work efficiency is equal to the real hours minus the standard hours plus the standard rate.

    (AH - SH) * SR = Variation in work efficiency.

    Therefore, if the actual hours are greater than the standard hours, an unfavorable variation occurs.

    AH > SH = unfavorable variation.

    AH < SH = favorable variation.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If the labor efficiency variance is unfavorable, then a. standard hours allowed for the actual output exceeded actual hours. b. the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.