Resources are not usually hired on a day-to-day basis to meet fluctuating requirements. This means that a. the maximum number of project resources should be hired for the project duration. b. if the workers are employed for the duration of the project and it may be necessary to pay them when idle or overtime when at peak demand. c. the actual work performed for each activity should be evaluated to inform the next activity of the number of workers needed. d. all projects should plan all tasks for one person to complete the activities to keep the person busy.

+3
Answers (1)
  1. 23 September, 12:16
    0
    C. the actual work performed for each activity should be evaluated to inform the next activity of the number of workers needed.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Resources are not usually hired on a day-to-day basis to meet fluctuating requirements. This means that a. the maximum number of project ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers