The following budget data are available for Sharp Company: Estimated direct labor hours 12,000 Estimated direct labor dollars $90,000 Estimated factory overhead costs $180,000 Actual direct labor hours 11,500 Actual direct labor dollars $92,000 Actual factory overhead costs $181,000 If factory overhead is applied based on direct labor hours, the amount of overhead to be applied is

A.) $181,000B.) $172,500C.) $180,000D.) $184,000

+3
Answers (2)
  1. 1 July, 05:16
    0
    Option B is correct option $172,000
  2. 1 July, 07:41
    0
    B.) $172,500

    Explanation:

    $180,000/12,000 hours = $15*11,500

    = 172,500

    Therefore, The amount of overhead to be applied is $172,500
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The following budget data are available for Sharp Company: Estimated direct labor hours 12,000 Estimated direct labor dollars $90,000 ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers