Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in September 2023, at an estimated cost of $22,000,000. At the end of 2021, the costs to date were $10,120,000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $4,800,000 and the cash collected during 2021 was 3,200,000. Cooper uses the percentage-of-completion method.

For the year ended December 31, 2021, Cooper would recognize gross profit on the building of:

+2
Answers (1)
  1. 17 May, 23:41
    0
    Cooper would recognize gross profit on the building of $920,000.

    Explanation:

    % of completed

    = cost incurred / estimated cost

    = $10,120,000/$22,000,000

    = 46%

    Revenue to be recognized

    = $24,000,000*46%

    = $11,040,000

    Gross profit

    = $11,040,000 - $10,120,000

    = $920,000

    Therefore, Cooper would recognize gross profit on the building of $920,000.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.