Ask Question
9 May, 17:53

The following standards for variable manufacturing overhead have been established for a company that makes only one product:

Standard hours per unit of output 7.0 hours

Standard variable overhead rate $ 13.40 per hour

The following data pertain to operations for the last month:

Actual hours 2,725 hours

Actual total variable manufacturing overhead cost $ 37,195

Actual output 150 units

What is the variable overhead efficiency variance for the month?

+3
Answers (1)
  1. 9 May, 18:40
    0
    variable overhead efficiency variance = $22,780 unfavorable

    Explanation:

    Giving the following information:

    Standard hours per unit of output 7.0 hours

    Standard variable overhead rate $ 13.40 per hour

    Actual hours 2,725 hours

    The actual output of 150 units

    To calculate the variable overhead efficiency variance, we need to use the following formula:

    variable overhead efficiency variance = (Standard Quantity - Actual Quantity) * Standard rate

    Standard quantity = 150*7 = 1,050 hours

    variable overhead efficiency variance = (1,050 - 2,750) * 13.4

    variable overhead efficiency variance = $22,780 unfavorable
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The following standards for variable manufacturing overhead have been established for a company that makes only one product: Standard hours ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers