The budget for the month of May was for 11,200 units at a direct materials cost of $19 per unit. Direct labor was budgeted at 28 minutes per unit for a total of $100,800. Actual output for the month was 8,900 units with $137,500 in direct materials and $81,775 in direct labor expense. The direct labor standard of 28 minutes was obtained throughout the month. Variance analysis of the performance for the month of May would show a (n) : (CMA adapted)
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The budget for the month of May was for 11,200 units at a direct materials cost of $19 per unit. Direct labor was budgeted at 28 minutes ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.