Ask Question
5 February, 13:49

The records at smith and jones, inc. show that job 110 is charged with $12,000 of direct materials and $11,000 of direct labor. smith and jones, inc. allocate manufacturing overhead at 85% of direct labor cost. what is the total cost of job no. 110?

+5
Answers (1)
  1. 5 February, 17:43
    0
    To solve:

    Direct marterial cost = $12,000

    Direct labor cost = $11,000

    Manufacturing overhead = 85% of direct labor cost = $9,350

    Add up all of the costs for the total cost of Job No. 110.

    $12,000 + $11,000 + $9,350 = $32,350.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The records at smith and jones, inc. show that job 110 is charged with $12,000 of direct materials and $11,000 of direct labor. smith and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers