If project A generates $10 million of free cash flow over its five year useful life and project B generates $8 million of free cash flow over its useful life, then Project A will have a shorter payback period than Project B, assuming both projects require the same initial investment.

+1
Answers (1)
  1. 17 March, 12:23
    0
    Answer: False

    Explanation:

    This seems to me like a True or False question and the answer would be False.

    Payback period is calculated on the basis of the timing of cash flows and since we do not know the useful life of Project B neither do we know the timing of it's cash flows, we cannot say for certain that Project A has a shorter Payback period.

    For example, the initial investment could be $5 million for instance but Project A only pays $10 million on its 5th year whereas Project B had a useful life of 4 years and paid $2 million each of those years. Meaning it would have paid back before the end of the 3rd year.

    If you need any clarification do react or comment.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If project A generates $10 million of free cash flow over its five year useful life and project B generates $8 million of free cash flow ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.