Sarasota company manufactures pillows in the cutting and assembly process. pillows are manufactured in 40-pillow batch sizes. the cutting time is 4 minutes per pillow. the assembly time is 8 minutes per pillow. it takes 10 minutes to move a batch of pillows from cutting to assembly. what is the value-added lead time?

a. 10 minutes

b. 22 minutes

c. 12 minutes

d. 8 minutes

+5
Answers (1)
  1. 27 July, 00:12
    0
    Answer: c. 12 minutes

    Value added time is the amount of time it takes to actually produce and improve a product. In the case of Sarasota company who manufactures pillows, value added time is the production time which is 4 minutes in cutting and 8 minutes in the assembly, total of 12 minutes.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sarasota company manufactures pillows in the cutting and assembly process. pillows are manufactured in 40-pillow batch sizes. the cutting ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers