Reynolds Manufacturers Inc. has estimated total factory overhead costs of $116,000 and expected direct labor hours of 11,600 for the current fiscal year. If job number 117 incurs 1,700 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for

+5
Answers (1)
  1. 10 March, 10:26
    0
    Overhead = $17,000

    Explanation:

    Giving the following information:

    estimated total factory overhead costs of $116,000

    expected direct labor hours of 11,600

    Job number 117 incurs 1,700 direct labor hours

    First, we need to calculate the predetermined manufacturing overhead rate:

    Predetermined manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Predetermined manufacturing overhead rate = 116,000/11,600

    Predetermined manufacturing overhead rate = $10 per direct labor hour

    Now, we can determine the amount of allocated overhead:

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 10*1,700 = 17,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Reynolds Manufacturers Inc. has estimated total factory overhead costs of $116,000 and expected direct labor hours of 11,600 for the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.