If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.

(A) True

(B) False

+1
Answers (1)
  1. 29 November, 11:18
    0
    (A) True

    Explanation:

    A constraint occurs when the resources are scarce in respect to their requirement.

    Here, the resources are 4 times that is one machine is required 6 months from now, and already the current availability is of 4 machines.

    Thus for each one activity one earth mover is required which means we have plenty of resources in the form of such machine at present thus there is no scarcity or constraint of resources.

    Thus, the given statement is

    True
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.