A standard differs from a budget because a standard is a unit amount. none of these; a standard does not differ from a budget. is a predetermined cost. contributes to management planning and control.

+4
Answers (1)
  1. 19 May, 03:20
    0
    Standard cost is the amount management thinks should be incurred to produce a good or service. A standard differs from a budget because a standard is a unit amount. A budget on the other hand expresses a total amount. Using standard costs provides a basis for evaluating cost control.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A standard differs from a budget because a standard is a unit amount. none of these; a standard does not differ from a budget. is a ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.