10. Dixon Construction Company was awarded a contract to construct an interchange at the junction of U. S. 94 and Highway 30 at a total contract price of $15,000,000. The estimated total costs to complete the project were $12,000,000. (a) Make the entry to record construction costs of $7,200,000, on construction in process to date. (b) Make the entry to record progress billings of $4,000,000. (c) Make the entry to recognize the profit that can be recognized to date, on a percentage-of - completion basis.

+5
Answers (1)
  1. 4 January, 02:47
    0
    Journal Entry

    Explanation:

    Books of (Dixon Construction Company)

    Journal Entry

    Date Account Title and Explanation Debit Credit

    A. Construction in process A/c Dr. $7,200,000

    Cash / Accounts payable A/c $7,200,000

    (Being construction cost paid)

    B. Accounts receivables A/c Dr. $4,000,000

    Billing in progress A/c $4,000,000

    (Being record of billing in progress)

    C. Construction expenses A/c Dr. $7,200,000

    Construction in process A/c Dr. $1,800,000

    Revenue from construction A/c $9,000,000

    (Being income generate from contract)

    Note:

    Revenue from construction = Total contract (Construction in process / estimated total costs to complete)

    Revenue from construction = $15,000,000 ($7,200,000 / $12,000,000)

    Revenue from construction = $9,000,000

    Construction in process = Revenue from construction - Construction expenses

    Construction in process = $9,000,000 - $7,200,000

    Construction in process = $1,800,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “10. Dixon Construction Company was awarded a contract to construct an interchange at the junction of U. S. 94 and Highway 30 at a total ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.