Green Company is planning to introduce a new product with a 75 percent incremental unit-time learning curve for production in batches of 1,500 units. The variable labor costs are $55 per unit for the first 1,500-unit batch. Each batch requires 200 hours. There are $15,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 3,000 units

+5
Answers (1)
  1. 5 October, 03:34
    0
    210 hours

    Explanation:

    The learning curve rate can be found by log75%

    Ln0.75 = 0.12249

    1 batch requires 200 hours

    The 1500 units batch will require 200 hours

    For 3000 units there will be two batches of 1500 units each

    200 hours * 2 batches * 0.12249 * 4.5 = 210 hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Green Company is planning to introduce a new product with a 75 percent incremental unit-time learning curve for production in batches of ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers