Data on Gantry Company's direct labor costs are given below: Standard direct-labor hours 46,000 Actual direct-labor hours 45,000 Direct-labor efficiency variance-favorable$4,800 Direct-labor rate variance-favorable$9,000 Total direct labor payroll$207,000 What was Gantry's standard direct labor rate

+3
Answers (1)
  1. 11 August, 05:32
    0
    Answer

    Standard labour rate per = $4.8 per hour

    Explanation

    Labour efficiency variance is the difference between the actual time taken to achieve a given production output less the standard hours allowed for same multiplied by the standard labour rate

    Standard labour rate = Efficiency variance / Difference in hours

    Difference in hours = Standard hour - Actual hours

    = 46,000 - 45,000

    = 1000 hours

    Standard rate = 4,800/100o hours

    = $4.8 per hour