Simms Corp. had a favorable direct-labor efficiency variance of $6,000 for the period just ended. The actual wage rate was $0.50 more than the standard rate of $12.00. If the company's standard labor hours allowed for actual production totaled 9,500, how many actual labor hours did the firm work

+2
Answers (1)
  1. 31 December, 17:15
    0
    9,000 = actual hours

    Explanation:

    Giving the following information:

    Simms Corp. had a favorable direct-labor efficiency variance of $6,000 for the period just ended.

    The standard rate is $12.

    The company's standard labor hours allowed for actual production totaled 9,500, how many actual labor hours did the firm work.

    To calculate the actual hours, we need to use the direct labor efficiency variance formula:

    Direct labor time (efficiency) variance = (Standard Quantity - Actual Quantity) * standard rate

    6,000 = (9,500 - actual hours) * 12

    6,000 = 114,000 - 12*actual hours

    9,000 = actual hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Simms Corp. had a favorable direct-labor efficiency variance of $6,000 for the period just ended. The actual wage rate was $0.50 more than ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.