Ask Question
10 September, 19:40

What is the net present value of a project with the following cash flows if the discount rate is 15 percent? The project costs $48,100 Year 1 $15,600 Year 2 $15,600 Year 3 $28,900 Year 4 $15,200 Select one: a. More than $15; 000 b. $5,000-$10,000 c. Negative d. $10,000-$15,000 e. Zero to $5,000

+1
Answers (1)
  1. 10 September, 19:48
    0
    The correct answer is option e

    e. Zero to $5,000

    Explanation:

    Net Present Value (NPV) : This is one of the techniques available to evaluate the feasibility of an investment project. The NPV of a project is the difference between the present value of the cash inflows and the cash outflows of the project discounted at the required rate of return

    PV of cash inflows

    = $15,600 * (1.15) ^ (-1) + ($15,600 * 1.15^ (-2) + ($28,900 * 1.15^ (-3) ($15,200 * 1.15^ (-4)

    =53,053.92

    NPV = 53,053.92-48,100

    NPV = 4,953.927
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “What is the net present value of a project with the following cash flows if the discount rate is 15 percent? The project costs $48,100 Year ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers