Ask Question
28 February, 22:38

On june 15, 2018, sanderson construction entered into a long-term construction contract to build a baseball stadium in washington,

d. c., for $410 million. the expected completion date is april 1, 2020, just in time for the 2020 baseball season. costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions) :

+1
Answers (1)
  1. 28 February, 23:44
    0
    The answer is $15000000.

    Explanation:

    Gross profit in 2016 is $60000000, 2017 is $40000000 and 2018 is $50000000.

    Calculation of 2016 is = Estimated gross profit x (actual cost to date : total cost)

    = $60000000 x ($40000000 : $ 160000000)

    = $15000000

    The method remains same to calculate the gross of every year.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “On june 15, 2018, sanderson construction entered into a long-term construction contract to build a baseball stadium in washington, d. c., ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers