Ask Question
30 January, 03:48

ctual and budgeted fixed overhead $1,092,000 Standard variable overhead rate $27.00 per standard labor hour Actual variable overhead costs $137,144 Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.) The direct labor rate variance is

+5
Answers (1)
  1. 30 January, 06:43
    0
    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Explanation:

    Giving the following information:

    Actual and budgeted fixed overhead $1,092,000

    Standard variable overhead rate $27.00 per standard labor hour

    Actual variable overhead costs $137,144

    We weren't provided with enough information to calculate the direct labor rate variance. But I will provide the formula.

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Actual rate = actual direct labor costs/total actual hours worked
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “ctual and budgeted fixed overhead $1,092,000 Standard variable overhead rate $27.00 per standard labor hour Actual variable overhead costs ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers