A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, which was 150 units less than budgeted. The total budgeted direct labor cost for September was $117,600. The direct labor cost incurred during September was $111,850 and 13,450 direct labor-hours were worked.
The labor rate variance for the month was:
a) $5750 F
b) $1130 U
c) $5750 U
d) $1130 F
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Home » Business » A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, which was 150 units less than budgeted. The total budgeted direct labor cost for September was $117,600.