Andy, a contracting officer, is reviewing a Performance Based Payment (PBP) request from his contractor. The PBP event listed in the contract requires the contractor to complete the mock-up of a prototype unit for Government technical team review. The contractor has completed 99% of the mock-up, but ran into a delay with a 3rd tier subcontractor. The contractor informs Andy that the mock-up will be 99% complete at the time of the Government review. Based only on these facts, may Andy approve the PBP request at this time?

+5
Answers (1)
  1. 2 April, 02:21
    0
    Answer: No. Andy must not approve the PBP request at this time because it is not 100% complete.

    Explanation:

    Performance-based payment is the transfer of money after a measurable action has been taken or a performance target that has been predetermined has been met.

    In this scenario, we are told that the contractor has completed 99% of the mock-up, but ran into a delay with a 3rd tier subcontractor and that the contractor then inform Andy that the mock-up will be 99% complete at the time of the Government review. Dur to this, Andy should not approve this because the PBP event is not yet 100%. For payment to be approved, it must be 100%.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Andy, a contracting officer, is reviewing a Performance Based Payment (PBP) request from his contractor. The PBP event listed in the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers