Ask Question
8 June, 02:35

Which of the following is the correct formula to compute the predetermined overhead rate? Multiple ChoicePredetermined overhead rate = Estimated total units in the allocation base : Estimated total manufacturing overhead costs Predetermined overhead rate = Estimated total manufacturing overhead costs : Estimated total units in the allocation base CorrectPredetermined overhead rate = Actual total manufacturing overhead costs : Estimated total units in the allocation base IncorrectPredetermined overhead rate = Estimated total manufacturing overhead costs : Actual total units in the allocation base.

+1
Answers (1)
  1. 8 June, 06:19
    0
    Answer: The correct formula to compute the predetermined overhead rate is Predetermined overhead rate = Estimated total manufacturing overhead costs : Estimated total units in the allocation base.

    Explanation:

    For example:

    Estimated total manufacturing overhead costs = 5000000

    Estimated total units in the allocation base = 60000

    Total real units produced = 30000

    So, Predetermined overhead rate = 5000000 : 60000 = 83.33

    Real overhead cost = Predetermined overhead rate * Total real units produced.

    So Real overhead cost = 83.33 * 30000 = 2499900.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following is the correct formula to compute the predetermined overhead rate? Multiple ChoicePredetermined overhead rate = ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers