For its inspecting cost pool, Ellis Company expected overhead cost of $45,150 and 2,150 inspections. The actual overhead cost for that cost pool was $36,120 for 1,935 inspections. Calculate the activity-based overhead rate used to assign costs to the inspecting cost pool.

+2
Answers (1)
  1. 6 June, 17:05
    0
    Predetermined manufacturing overhead rate = $21 per inspections

    Explanation:

    Giving the following information:

    For its inspecting cost pool, Ellis Company expected overhead cost of $45,150 and 2,150 inspections.

    To calculate the predetermined manufacturing overhead rate we need to use the following formula:

    Predetermined manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Predetermined manufacturing overhead rate = 45,150/2,150

    Predetermined manufacturing overhead rate = $21 per inspections
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “For its inspecting cost pool, Ellis Company expected overhead cost of $45,150 and 2,150 inspections. The actual overhead cost for that cost ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.