One approach to reducing project length would be to: Group of answer choices Eliminate tasks on the critical path. Use hammock activities in place of multiple activities. Convert merge activities to burst activities. Convert parallel paths to be serial.

+4
Answers (1)
  1. 17 February, 22:52
    0
    the correct answer is Eliminate tasks on the critical path.

    Explanation:

    Critical path is the set of activities which are essential or "critical" for the success of the process. If we truly need to reduce the length of a project, we should find innovative ways to reduce the number of critical processes in the critical path.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “One approach to reducing project length would be to: Group of answer choices Eliminate tasks on the critical path. Use hammock activities ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.