Ask Question
15 January, 11:32

To effectively track the Sprint progress, Scrum mandates A. Preparing Sprint burn down charts B. Increasing the transparency by frequently updating the remaining work C. Earned Value approach

+1
Answers (1)
  1. 15 January, 14:42
    0
    The answer is option A To effectively track the Sprint progress, Scrum mandates Preparing Sprint burn down charts

    Explanation:

    Sprints are time-boxed periods of one week to one month, during which a product owner, scrum master, and scrum team work to complete a specific product addition. During a sprint, work is done to create new features based on the user stories and backlog. A new sprint starts immediately after the current sprint ends.

    Some scrum teams deploy new product features for use at the end of each sprint. For scrum teams with a release with every sprint, the time to market is simply the sprint length, measured in days.

    A sprint burn down chart shows the progress the development team is making and is a powerful tool for visualizing progress and the work remaining.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “To effectively track the Sprint progress, Scrum mandates A. Preparing Sprint burn down charts B. Increasing the transparency by frequently ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers