Ask Question
26 November, 12:00

For the project activities below: Answer questions 44-46: Normal Crash Crashing Costs/Wk Activity Precedes Time (wk.) Times ($ 000) / Wk A C, D 6 5 8 B G 4 2 6 C E 4 4 - - D F 5 3 6 E H 6 4 8 F H 6 4 10 G I 8 6 5 H End 5 3 12 I End 6 5 5 44. What activities make up the critical path

+3
Answers (1)
  1. 26 November, 13:44
    0
    Options C and E are correct

    Explanation:

    BGI and ADFH makes up the critical path
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “For the project activities below: Answer questions 44-46: Normal Crash Crashing Costs/Wk Activity Precedes Time (wk.) Times ($ 000) / Wk A ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers