Ask Question
2 September, 22:54

Under the BOT option for a project:

a. The customer organization transfers employees to the project organization for the duration of the project.

b. The customer organization must accept the work product of the project at the scheduled delivery date.

c. The project organization must operate the work product of the project for a while.

d. The project organization may build the work product to their own specifications instead of the customer.

+4
Answers (1)
  1. 3 September, 00:56
    0
    The correct answer is the option C: The project organization must operate the work product of the project for a while

    Explanation:

    To begin with, the name of "Build-operate-transfer" or BOT is used to refer to a form of project delivery method in where a private entity receives the concession from the public sector with the only purpose of financing, constructing, own and operate a facility stated previously in the contract done by all the parties. Therefore that this type of method is used in large scale infrastructure projects with the purpose of making the process easier.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Under the BOT option for a project: a. The customer organization transfers employees to the project organization for the duration of the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers