Ask Question
18 February, 07:24

Sweet Dreams, Inc. manufactures bedding sets. The budgeted production is for 52,000 comforters in 2012. Each comforter requires 1.5 hours to cut and sew the material. If cutting and sewing labor costs $11.00 per hour, determine the direct labor budget for 2012.

+3
Answers (1)
  1. 18 February, 10:29
    0
    Direct labor budget = $858,000

    Explanation:

    Giving the following information:

    The budgeted production is for 52,000 comforters in 2012. Each comforter requires 1.5 hours to cut and sew the material. If cutting and sewing labor costs $11.00 per hour.

    First, we need to calculate the total requirement of direct labor hours:

    Total direct labor hours = 52,000 units*1.5 = 78,000 hours.

    Direct labor budget = 78,000 hours * $11 = $858,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sweet Dreams, Inc. manufactures bedding sets. The budgeted production is for 52,000 comforters in 2012. Each comforter requires 1.5 hours ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers