Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,200 of direct materials and used $4,700 of direct labor. The job was not finished by the end of September, but needed an additional $3,700 of direct materials in October and additional direct labor of $7,200 to finish the job. The company applies overhead at the end of each month at a rate of 150% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October

+2
Answers (1)
  1. 1 June, 10:24
    0
    Total job Costs added to Work In Process in October=$ 21, 700

    Explanation:

    Jaycee Corporation

    Direct Materials requisitioned $3,200

    Direct labor $4,700

    Over head = 150% 0f $ 4700 = $ 7050

    Total Costs Added During September = $ 3,200 + $ 4,700 + $ 7050 = $ 14950

    Costs Added During October

    Direct Materials $3,700

    Direct labor $7,200

    Overhead = 150 % 0f $ 7,200 = $ 10,800

    Total job Costs added to Work In Process in October = $ 3,700 + $ 7,200 + $10,800 = $ 21, 700
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,200 of direct ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.