Ask Question
29 March, 17:36

Which section of the project charter publicly acknowledges the commitment of the sponsor, managers and team members to the project? a. decisions and findings b. contract section c. signatures and commitment d. business case

+3
Answers (1)
  1. 29 March, 20:30
    0
    The correct answer is letter "C": signatures and commitment.

    Explanation:

    A Project Charter is the document that makes official the beginning of a project and officially names the manager of the project and defines the main objectives and restrictions that the executive must achieve. Thus, it is one of the most important documents in the beginning phase of the project.

    The commitment of the sponsor, managers, and team members is recorded in the signature and commitment area of the project where investors, executives, and employees confirm they will drive all their efforts to reach their common goal.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which section of the project charter publicly acknowledges the commitment of the sponsor, managers and team members to the project? a. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers