Ask Question
7 May, 17:16

Floor-On, Ltd., operates a line that produces self-adhesive tiles. This line consists of single-machine stations and is almost balanced (i. e. station rates are nearly equal). A manufacturing engineer has estimated the bottleneck rate of the line to be 2,000 cases per 16-hour day and the raw process time to be 30 minutes. The line has averaged 1700 cases per day, and the cycle time has averaged 3.5 hours. What would you estimate the WIP level to be

+1
Answers (1)
  1. 7 May, 19:08
    0
    The correct answer is 372 cases.

    Explanation:

    According to the scenario, the given data are as follows:

    Average cases per day = 1,700

    Total hours in one day = 16 hour

    So, Average cases per hour = 1,700 : 16 = 106.25 cases

    cycle time = 3.5 hours

    So, we can calculate the WIP level by using following formula:

    WIP = Average cases per hour * cycle time

    = 106.25 * 3.5

    = 372 Cases (approx.)

    Hence, the WIP level is 372 cases.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Floor-On, Ltd., operates a line that produces self-adhesive tiles. This line consists of single-machine stations and is almost balanced (i. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers