Ask Question
29 May, 05:46

Assembly department of Zahra Technologies had 200 units as work in process at the beginning of the month. These units were 45% complete. It has 300 units which are 25% complete at the end of the month. During the month, it completed and transferred 600 units. All direct materials are added at the beginning of production. Conversion costs are allocated evenly throughout production. Zahra uses weighted-average process-costing method. What is the number of equivalent units that should be used for assigning costs to work completed with regard to direct materials

+4
Answers (1)
  1. 29 May, 09:33
    0
    Total equivalent units of material = 900

    Explanation:

    Equivalent units are notional whole units which represent incomplete works are used to allocate cost to work in progress and completed units

    Under the weighted average method of valuation, to account for completed units, it is assumed that the entire degree of work required is done in the period under consideration. So there is no separation of the completed units into opening inventory and fully worked.

    Equivalent unit = Degree of completion * units

    Item units Equivalent units

    Completed units 600 100% * 600 = 600

    Closing inventory 300 100% * 300 = 300

    Total equivalent units of material 900

    Note simply because materials are added at the beginning of the process, it is assumed that all the quantity required would have been added. Hence the degree of completion for materials is 100%.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Assembly department of Zahra Technologies had 200 units as work in process at the beginning of the month. These units were 45% complete. It ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers