Dubberly Corporation's cost formula for its manufacturing overhead is $31,600 per month plus $52 per machine-hour. For the month of March, the company planned for activity of 8,100 machine-hours, but the actual level of activity was 7,980 machine-hours. The actual manufacturing overhead for the month was $476,410. The activity variance for manufacturing overhead in March would be closest to:

+4
Answers (1)
  1. 29 December, 09:09
    0
    The activity variance for manufacturing overhead in March would be closest to $6240

    Explanation:

    As per given Data

    Total overheads = $31,600 + (Machine hours x $52)

    Bu using this equation we will calculate the activity variance

    Planned machine hours = 8,100 hours

    Placing value in the formula

    Planned Manufacturing overheads = $31,600 + (8,100 hours x $52)

    Planned Manufacturing overheads = $452,800

    Actual machine hours = 7,980 hours

    Applied Manufacturing overheads = $31,600 + (7,980 x $52)

    Applied Manufacturing overheads = $446,560

    Activity Variance for manufacturing overhead = Planned Manufacturing overheads - Applied Manufacturing overheads

    Activity Variance for manufacturing overhead = $452,800 - $446,560 = $6,240
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Dubberly Corporation's cost formula for its manufacturing overhead is $31,600 per month plus $52 per machine-hour. For the month of March, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.