List problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in the bid documents

+1
Answers (1)
  1. 3 August, 00:59
    0
    problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in the bid documents are unbalanced bids in unit prices on which periodic payment estimates are based. change orders subject to negotiated payments changes in design or construction technology incentives for early completion
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “List problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.