The estimated variance for an activity with a most likely time (m) equal to 11 days, the optimistic time (a) equal to 6 days, and the pessimistic time (b) equal to 18 days is

+1
Answers (1)
  1. 24 October, 11:08
    0
    4 days. This has to do with business management and the idea that different types of time based on the mindset varies between how much work and activity will actually be done.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The estimated variance for an activity with a most likely time (m) equal to 11 days, the optimistic time (a) equal to 6 days, and the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.