If one of the activities on the critical path is delayed, the entire project will be delayed.

b. the critical path is the sequence of activities between a project's start and finish that takes the shortest time to complete.

c. there may be more than one critical path in a project network.

d. the activities along the critical path determine the completion time of the project.

+3
Answers (1)
  1. 8 January, 12:07
    0
    Must be d all activities must be completed for project completion
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If one of the activities on the critical path is delayed, the entire project will be delayed. b. the critical path is the sequence of ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.