What must a project manager do before creating a dependency schedule?
A. Identify which tasks must be completed by the project manager.
B. Identify which tasks will involve the most teamwork.
C. Identify which tasks can be skipped.
D. Identify which tasks are primary and which are dependent.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “What must a project manager do before creating a dependency schedule? A. Identify which tasks must be completed by the project manager. B. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.