Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour Step 3: rate = 240 seats per hour What is the fastest rate at which the assembly line can produce complete bicycles?

+1
Answers (2)
  1. 27 February, 19:15
    0
    60 bicycles

    Explanation:

    The slowest step determines the overall rate of the process.
  2. 27 February, 21:10
    0
    Answer:60 and slowest determines overall

    Explanation:

    I took the warm up assignment
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour ...” in 📙 Chemistry if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.