There are two activities on your schedule, which are: 1) install server in lab 2) move server into the data center. however, the second task can't start until the server has run in the lab for 5 days without failure. this is an example of what?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “There are two activities on your schedule, which are: 1) install server in lab 2) move server into the data center. however, the second ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.