The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

+1
Answers (1)
  1. 27 October, 13:54
    0
    D is correct option

    Explanation:

    D. longest time path through the network.

    The sequence of activities within the network with zero total float is called critical path.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.