During the initiating phase, a project charter authorizes a project to begin. Which of the following elements are included in a project charter? (Choose all that apply)

a. Problem statement

b. Project objectives

c. Risk assessment

d. Stakeholder identification

+3
Answers (1)
  1. 3 May, 10:24
    0
    A. Problem statement

    b. Project objectives

    d. Stakeholder identification
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “During the initiating phase, a project charter authorizes a project to begin. Which of the following elements are included in a project ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.