Sayeed needs to ensure that his manager is up to date on his progress and wants to send a Status Report for a particular task. In which command group will he find this option within the Task form?

+1
Answers (1)
  1. 18 April, 04:33
    0
    Project - -> status - -> status date

    Explanation:

    If we want to share the status of a task or an entire project in Microsoft project, we can use the status date, and we could get theoretical progress, in addition, we could add progress about two dates.

    For example:

    If we have a construction, this construction will take 100 days, we could show the progress in the first two months, 60 days, in this case, would be 60% of progress, this would be in date format, 21/01/2020 to 21/03/2020.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sayeed needs to ensure that his manager is up to date on his progress and wants to send a Status Report for a particular task. In which ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers