Ask Question
21 November, 01:37

An over-target baseline (OTB) is a comprehensive rebaselining effort that is best categorized as an internal replanning effort.

A. True

B. False

+1
Answers (1)
  1. 21 November, 02:26
    0
    The answer is "option B".

    Explanation:

    An OTB stands for an over-target baseline, it is a new management benchmark when an original target can't have coincided and new goals for management purposes are required.

    It is also known as a reference to the foundation for calculating or constructing. It is an understanding between the client and the contractor that the cost base, which is not part of the original contract budget, should include an extra budget
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “An over-target baseline (OTB) is a comprehensive rebaselining effort that is best categorized as an internal replanning effort. A. True B. ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers