Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost. A. TrueB. False

+3
Answers (1)
  1. 1 March, 06:08
    0
    Answer: False

    Explanation: Because fast-tracking doesn't involve additional resources, it's usually best to start with this technique while Crashing requires careful planning to prevent "panic mode" among the project crews and to avoid acceleration claims.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.